Schools and Education
Wilde Consulting Engineers have recently undertaken and completed designs for nine new build school projects, SureStart community centres and leisure facilities. These designs were carried out through Framework Contracts with a number of Local Authorities.
Structural surveys, remedial works designs and specifications for repairs and refurbishments have been carried out on over 50 schools during the last 10 years. In addition to defect reports, many of the commissions are Architect led. Projects have involved providing DDA compliance, replacing flat roofs, extensions and modernisation.
Design features and challenges addressed during these projects include:
• Complex geometries, with building curves on plan and in elevation
• Mixed structural materials – steel, glulaminated timber and masonry
• Concrete framed construction
• Contemporary and sustainable building materials
• Rain water attenuation and SUDS
• Sloping and congested sites
• Phased construction
• Roads and car parks
• Ground contamination
• Land quality and remediation statements
• Three dimensional modelling
• Value Engineering
• NBS Specifications
The case studies below illustrate the depth and extent of our expertise.
|
Relevant Case Studies...
Waterloo Sure Start Facility
• Arrange and manage site investigation (geotechnical and contamination)
• Structural survey, inspection and arrange material testing of existing building
• Cost options study for refurbishment and extension of existing versus demolition and new build
• New build masonry structure, following demolition of previous derelict structure
Lyndhurst Primary School
• Steeply sloping and congested site. New storey high retaining walls to achieve required building footprint
• New build phased with phased demolition of existing school
• Multi storey steel framed
• Ground contamination: benzo a pyrene and other contaminants
• Contemporary building materials for structural components; Ziegel blocks, calcium silicate masonry, Fermacel partitions
Wellacre Sixth Form College
• Insitu reinforced multi storey concrete frame and slab construction
• BREEAM low energy design
• Passive ventilation throughout
• Internal Atrium, elevated walkways and meeting areas
Fir Tree Primary School
• Structural Survey and report with cost estimates for structural repairs prior to commitment to roofing contract
Aldwyn Primary School
• Building curved on plan and elevation; therefore building frame lines not straight
• Mixed steel and glu-laminated timber frames
• Contemporary building materials for structural components; Ziegel blocks, calcium silicate masonry, Fermacell partitions
• Rain water attenuation design: green roof, buried tanks and flow limit controls
Arden Primary School
Oxford Park Community Centre and Sports Hall
• Mixed steel and timber frame construction
• Integrated within existing park layout and features
• Community liaison
Ravensfield Primary School
• Site clearance and demolition of existing school
• Design and layout for new highway and external car park
• Rainwater attenuation design
• Congested and steeply sloping site – multiple retaining walls
Ridge Hill Sure Start Facility
• Steeply sloping and congested site. New storey high sheet piled retaining walls to achieve required building footprint
• New build works carried out within congested live school site
• Two storey combined steel and glu-laminated timber frame structure
• Ground contamination; benzo-a-pyrene and other contaminants
St. Peters Sure Start Facility
• Steeply sloping and congested site. New storey high sheet piled retaining walls to achieve required building footprint
• New build works carried out within congested live school site
• Two storey combined steel and glu-laminated timber frame structure
• Ground contamination; benzo-a-pyrene and other contaminants
• Timber framed single storey construction
• Vibro compaction ground improvement works of poor ground and infilling of existing cellars
• Congested city centre site
Marple Hall High School
• Concrete inspection and repair specification
• Design and detailing of cladding fixings
• Health and safety method statements
Walkden High School
• Intrusive investigations focusing on possible timber degradation at key structural locations
• Report recommending limited remedial works for life extension